試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You have just finished most of the work on a new system integration project when the seller comes to you with detailed procedures for close out of the contract. The contract included closeout procedures. What should the project manager do?
A、 Revise the closeout procedures after getting management’s approval.
B、 Get a change order.
C、 Create new procedures that are more complete.
D、 Assess the quality of the seller’s new detailed procedures and if they are better than the current procedures.use them.