試題題型【單選題】
試題內(nèi)容


After estimating activity durations and activity resources, the project manager arrived at a project schedule network diagram. This table shows date that supported the diagram. The project manager requested 8 developers for activity . however, due to the Organization’s constraints, the project manager is provided with 2 developers. What technique should the project manager use to re-calculate the new finish date?
A. Critical chain method.
B. Monte Carlo analysis.
C. Benchmarking.
D. Resource Leveling.